| | County | Wolfe | City | City of Campton |
| | Project Name | Campton Pedway Project |
| | Project Applicant | City of Campton |
| | Project Engineer | Wayne Simmons - Nesbitt Eng. |
| | Project Administrator | Eunice Fitzpatrick |
| | Project Category | Pedways |
| | Project Outline | The proposed project will use Enhancement Funds to create |
| | an extend the current pedway in the downtown area. Sidewalks |
| | in Campton east and west of Hwy 15. 3 phases 1) 2600' |
| | west of Hwy 15 2) 1450' east of Hwy 15 3) 2300' |
| | continued east of Hwy 15 |
| | Status | The Engineer has been selected. Project Design will begin |
| | soon. |
| | Comments | Funding was awarded in the amount of $175,000 on June 30, |
| | 2006. |
| | Funding Source List | Amount |
| | Local Match | $47,360.00 |
| | TEA-21 (TE) (GOLD) | $189,440.00 |
| | Subtotal | $236,800.00 |